Summarizing approach and organizing legal docs for our pilot projects

Feb 22 2023 Update

FPO

Resource Institution

Funds Flow

Amount

Timing

Asset

Links to Executed Agreements

Read More

Saharapada

CYSD

DGF → DGT → Collaboration agreement between DGT and FO (asset belongs to DGT, is written off as project expense)

INR 15 lakh

Complete, established July 2022

Polyhouse for vegetable saplings incl tomato, brinjal

Collaboration Agreement (need link)

Investment Summary

Annapurna

Jattu Trust

DGF → Velugu (which has FCRA) and will figure out arrangements with Jattu and Velugu supported FOs.

INR 15 lakh

Feb 2023

Collection Center to setup a oilseed processing unit (sesame, groundnut)

Investment Summary

Girivikasam MACS

Velugu Association

INR 30 lakh

March 2023

Cold Room for cashew, turmeric, pineapple

Investment Summary

TBD

TBD

TBD, will not use DGT NFCRA funds

INR 25 lakh

June 2023

Compost unit / bio-fertilizer

Investment Summary

Aug 22 2022

FPO

Resource Institution

Funds Flow

Links to Executed Agreements

Saharapada

CYSD

DGF → DGT → Collaboration agreement between DGT and FO (asset belongs to DGT, is written off as project expense)

Annapurna

Jattu Trust

DGT → FO (Using not FCRA funds)

Girivikasam MACS

Velugu Association

DGF → Velugu → Velugu and Girivikasam will figure out an agreement between themselves