More detailed and longer duration plan to support this work under development
Week | Actions | Outcomes | Status |
---|---|---|---|
Sep 12 | Planning meetings in BLR | Alignment on what product offering, roles and responsibilities | Complete |
Sep 19 | Co-design session with program team in BLR | Refine user personas, user journey and initial set of designs Buy-in from program team on product direction | Complete. D2FO Product Exercise Miro |
Sep 26 | ETH, KEN, US team members in India | Global alignment on type of FPOs we will focus on Design release | Complete. Actions items captured here |
Oct 3 | User feedback on design Review wireframes with state leads and others | Internal buy-in on product direction Begin revising design based on user feedback | Review product designs with state leadership in Delhi on Oct 21 |
Oct 10 | Design release | Start development sprint | Expect this will start mid November |