Total Budget :

...

Total cost - 141,03749,168.00 INR ( Rs 14,0338,168 by DG ) FPO contribution : Rs 13,02,000

...

Particulars 

...

Cost (INR)

11,000.00 INR

Budget for Poly House Nursery for FPO

Sl no

Particulars

Unit

Rate

Amount

Source

1

Entry point Activities for establishment of Poly House

1.1

Land Levelling (7hrs)

7

2000

14000

DG

1.2

Electric Wire (Lump Sum)

LS

15000

15000

DG

1.3

Water delivery pipes (150 mtrs)

150

100

15000

DG

1.4

Nursery Input Materials (Lump Sum)

LS

35000

35000

DG

1.5

Misc. Expenses (Lump Sum)

LS

6000

6000

DG

Sub Total Entry Point Activities

85000

2

Nursery Establishment expenses

2.1

Construction of poly house of 480 sqm . (includes

seedling materials ,over head

overhead micro irrigation of 1000 lit water tank and minimum 1 hp mono block pump set)

10,59,168.00

DG

Seedlings 

1,00,000.00

DG

Labour & maintenance

1,00,000.00

FPO

Data officer (for 8 months )

1,44,000.00

DG

Total

14,03

1

1059168

1059168

DG

2.2

Seeds
(10gm seeds@Rs. 500/10gm from which we will get 1000 seedlings. As a result 200000 seedlings we require 200 pacs) (200pkts X Rs. 500 = 100000)

1

100000

100000

DG

2.3

Water lifting for operation @ Rs 500/ month for 12 months

6,000

FPO

2.4

Land lease cost ( @Rs 1000/year for 10 years

10,000

FPO

2.5

Electricity charges @ Rs 750/month for 12 months .

9,000

FPO

2.6

Pump set

8,000

FPO

2.7

Watch & Ward(@3000/month for 12 months

36,000

FPO

2.8

Labour cost (10 Man days per month @ Rs 300 per day for 10 months )

36,000

FPO

2.9

Bore well ( Convergence with govt. )

200,000

FPO

2.10

Unforeseen Expenditure

6,000

FPO

Sub Total Nursery Establishment expenses

1470168

3

Training

3.1

Training and capacity building (Lump sum)

LS

50000

50,000

DG

Sub Total Training

50,000

4

Operational Cost

4.1

Data officer (2 data officers @ 9000/month for 8 months )

9000

16

144000

DG

Sub Total Operational Cost

144000

Grand Total

1,749,168

PLAN :

S.No

Milestone 

Time line

1

Project Finalization 

May 15th

2

Project Plan & Budget preparation

June 1-10

3

Vendor selection

June 10-15

4

Poly house set up

july 5-10

5

Funding disbursed

july 5-10

6

Demand collection (seedling)

July1-15

7

Data collection ( Nursery )

July -15-Aug 30

8

First Sapling Sales

Aug-15

9

Training ( convergence with Horticulture Dept)

Aug-15-30

10

Impact (Vegetables produced from poly house sampling)

Oct-30

...