Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

S.No

Milestone 

Time line

1

Project Finalization 

May 15th

2

Project Plan & Budget preparation

June 1-10

3

Vendor selection

June 10-15

4

Poly house set up

july 5-10

5

Funding disbursed

july 5-10

6

Demand collection (seedling)

July1-15

7

Data collection ( Nursery )

July -15-Aug 30

8

First Sapling Sales

Aug-15

9

Training ( convergence with Horticulture Dept)

Aug-15-30

10

Impact (Vegetables produced from poly house sampling)

Oct-30

FPO Contribution Details: ashok Amrita Das (Unlicensed) Ronali Pradhan (Unlicensed) Ashu Sikri (Unlicensed)

S.No

Particulars

Rate
(INR)

Unit
(month/unit)

Amount
(INR)

Remarks

1

Water lifting charges @ Rs. 500/month for 12 months

500

12

6000

The FPO has rented a well from a near by place which will provide water required for the nursery. The amount will be paid to the owner by the FPO.

2

Land lease cost @Rs. 1000/year for 10 years

1000

1

1000

Plot of land where proposed enclosed nursery will be setup. The FPO has bore the amount as a cost of lease agreement between government and FPO.

3

Electricity charges @ Rs. 750/month

750

12

9000

FPO is planning to get the electricity connection from the department which will cost around Rs 40000. As the process will take time the FPO has arranged the electricity from the near by place to whom the FPO will be paying the bills as per the usage. This connection will be used for the operation of the water sprinkler.Water will be lifted to tank using a water pump.

4

Water lifting using a pump

8000

1

8000

To be installed near a well to lift the water to the overhead tank

5

Watch & ward @Rs. 3000/month

3000

12

36000

Two persons will be appointed to watch and guard the nursery day and night. FPO will be paying the wages. An amount Rs 2000 will be paid to the day watcher, similarly a wage of Rs1000 to the night watcher.

6

Labour Cost
(10 mandays per month @Rs.300 per mandays for 10 months)

3000

12

36000

10 human resources are required for sowing the seeds in the tray in a month, weeding of the nursery and other operational activities.

7

Unforeseen Expenditure

6000

1

6000

Records/stationary items for book keeping and other cost.

Total

102000

**

One Bore Well (Convergence)

200000

1

200000

A bore well is required to provide adequate water supply for irrigation of the seedlings. The FPO has applied for the borewell facility under a government scheme.