Context: What we plan to do over the upcoming ~6 weeks ~8 to 10 weeks (late Feb through April 2022) so that we can develop a credible "roadmap" (or at least high level list of objectives / deliverables / activity areas along with resource needs) ready in line with the annual planning timeline (initial pass late March and finalize in April).
Key Dates / Milestones:
Ashu Sikri (Unlicensed) to send weekly updates highlighting key activities and progress vs goal
Week | Dates | Key Items (Expected) | Key Items (Actual) |
---|---|---|---|
1 | Feb 21 to 25 |
| |
2 | Feb 28 to Mar 4 |
| |
3 | Mar 7 to 11 |
| |
4 | Mar 14 to 18 |
| |
5 | Mar 21 to 25 |
| |
6 | Mar 28 to Apr 1 |
| |
7 | Apr 4 to 8 | ||
8 | Apr 11 to 15 |
| |
9 | Apr 18 to 22 | ||
10 | Apr 25 to 29 |
|
Deliverables at the end of this process?
DFN budgets for India, Ethiopia and Kenya; first pass ready by week of March 28
Any Call out intersection points between DFN and existing projects like TARA or ATLAS?
See annual planning slides here. Key questions:
What is the objective and key measures of success?
Staffing needs? (existing and new). See below
What are the main cost drivers and associated assumptions?
Any requests or dependencies from cross-cutting teams? (i.e. comms, MEL, Advocacy, gender, climate, strategy and tech)
What are the risks that require mitigation?
...
Role
...
Contribution
...
Status
...